Construction Projects
 
 


2009 Asphalt Overlay


This project consists of profile “milling”, along with hot mix asphalt overlay of specified streets through the City of Muscatine and then adjusting existing manholes to fit the newly overlaid surface. Contractor: Illowa Investments, Inc. of Blue Grass, Iowa
Project Manager: Jim Harder

Asphalt Overlay Overlay Completed in Spring 2010:

Lincoln Blvd. from Jackson St. to Clay St.
Washington Street from Park Ave. to the Mad Creek Bridge
Greenwood Cemetery

Asphalt Overlay to be Completed:

#1 alley from Mulberry Ave. to Pine St.
#2 alley from Mulberry Ave. to Pine St.
#3 alley from Mulberry Ave. to Pine St.
#4 alley from Mulberry Ave. to Pine St.
#5 alley from Mulberry Ave. to Pine St.